SBA LoanBusiness planningStart planning
Menu

How to inspect laundromat utilities before signing a lease

Updated · By SBA Loan editorial

Operational worked example · Leased coin/card laundromat; no dry cleaning or wash-and-fold

Inspect the unit against the exact proposed equipment schedule, then obtain written provider capacity confirmation and coordinated installation bids. Check average utility cost and instantaneous service capacity separately. A former laundromat, a large gas pipe or a low monthly water bill does not establish that a new washer/dryer mix will work. Make approval, external upgrades and payment responsibility explicit before a binding lease.

Read the complete operating guide set · Browse operating articles

Bring a complete equipment schedule to the inspection

List every washer size, model/control option, voltage/phase, water inlet, expected cycle program and drainage arrangement. List both pockets of every stack dryer, gas input, electrical requirements, exhaust connection and make-up-air needs. Add the water heater, HVAC, kiosk, lighting and any other building loads. The same schedule should reach the equipment supplier, engineer, trades, utility providers and landlord so that each quote prices the same job.

The linked illustrative case uses 12 twenty-pound, eight forty-pound and four sixty-pound washers plus eight stacks containing 16 thirty-pound dryer pockets. The T-300, T-600 and T-900 sheets support reference capacities and approximate water use; the T-30x2 sheet identifies gas/airflow conditions. These reference configurations still need availability and exact SKU confirmation. Changing the series, extraction or heating option can change the design.

Collect records before treating installed services as reusable

Ask for available as-built plans, permits, inspection/occupancy records, meter/service sizes, panel schedules, gas-regulator information, existing equipment inventory and recent utility bills. Record which documents were actually received and who reviewed them. Bills can show consumption and tariff class; they rarely show the condition of buried drains, available transformer capacity or whether an old duct arrangement suits a new machine.

Walk the accessible service routes with qualified trades. Record dated photos and measurements of connection points, roof paths, slab conditions, drain access and lint-service clearances, with landlord permission. Identify unknown sections rather than declaring them acceptable. The equipment installer may understand anchoring; the utility is responsible for confirming its external service. Neither opinion replaces the other.

Check water fill, heater recovery and simultaneous drainage

The manufacturer reference water use is 15.8, 35.1 and 52.6 US gallons per cycle for the three sizes. At the assumed mature demand, the mix uses 2,465.0 gallons per day. That is a budgeting input, not a pipe-sizing calculation. Approximate cycle gallons divided by an hour can hide rapid fill or simultaneous drain events.

Ask the designer to evaluate available pressure/flow with concurrent equipment demand, hot-water storage/recovery and selected temperatures, drain discharge arrangement and downstream sewer conditions. Confirm any backflow, discharge, connection or impact-fee requirements with the responsible provider/authority. A test of one faucet is insufficient evidence for all machines filling together. Do not choose a drain diameter or pump merely from monthly gallons.

The case’s assumed water/heating and drainage trades total $52,000. The allowance includes inside piping/drain/slab work and excludes an unquoted public-main upgrade. Orange County’s plumbing process supports the application route, not this price or site acceptance. Get written scope and a project quotation; unknown external work is not a zero-cost line.

Use nameplate gas and airflow for coordination—not average burner duty

Exact arithmetic from the 60Hz reference dryer schedule. This is a preliminary engineering handoff, not a service certificate or common-duct design.
LoadCalculationResult
Dryer gas nameplate16 pockets × 90,000 Btu/h1,440,000 Btu/h
Assumed heater design targetAdditional selected plant to quote300,000 Btu/h
Combined preliminary gas loadDryers + assumed heater1,740,000 Btu/h
Dryer airflow reference16 pockets × 600 cfm9,600 cfm

The primary sheet also specifies inlet-pressure and exhaust-back-pressure conditions. Have the provider and engineer confirm service, regulator, piping, pressure, simultaneous loads and any permissible diversity for the selected equipment. Sum other building gas loads too. The model’s 60.0% average duty estimates consumption; it is not permission to size gas service at that fraction of nameplate.

Inspect duct routing, roof/wall rights, static-pressure design, make-up air, combustion safety, lint access and maintenance responsibility. The sum of pocket airflow does not establish a permissible shared duct, fan or opening area. Quote the designed arrangement and confirm inspections before assuming that an existing vent hole solves the exhaust system.

Confirm exact voltage, phase and the complete approval route

Record service voltage/phase and actual proposed machine variants. Ask the electrician for the load/branch schedule, protection, panel condition, grounding and any service/transformer upgrades. A 208–240V variant in a specification sheet cannot simply be connected to whatever service exists, and running amps do not substitute for a code-compliant branch design. Coordinate heater and HVAC loads as well as washers and gas-dryer motors.

The illustrative jurisdiction is unincorporated Orange County, Florida; its BTR procedure requires zoning approval for proposed new businesses. First confirm the parcel’s municipality. Obtain the responsible building, mechanical, electrical, fire, plumbing and accessibility requirements for the actual address. This article does not certify zoning, occupancy or permit readiness for a property.

Make quote boundaries and lease conditions inspectable

Inspection decision file to complete before commitment. Requested, received, technically checked and approved are different statuses.
SystemEvidence to obtainDecision to resolve
Water/sewerMeter/account data, design, provider capacity and impact-fee responseInside work versus external main/service upgrades
GasExact load schedule, provider confirmation and manifold designRegulator/service capacity, completion date and responsibility
ElectricalLoad/panel/branch design and utility transformer responseAvailable phase/service and outside upgrade cost
Dryer airDuct/make-up-air design, penetrations and inspection pathRoof rights, static pressure, maintenance and landlord consent
Commercial budgetCoordinated bids and payment milestonesTax/freight/permits/overlaps, funds before deposits
LeaseSite approvals, landlord works and review of conditionsRent start, upgrade responsibility and failed-approval exit

Use qualified lease/lender review to document the conditions and responsibilities. This is a decision checklist, not drafted contract language. Decide who pays for unknown mains, external transformer work and roof restoration, how long utility works may take, and when rent starts. Preserve quote validity and supplier lead times. An opening date that precedes service completion needs a revised preopening cash schedule.

Translate the inspection into the financial model

Obtain the actual provider/account-class tariff, fixed/demand charges, sewer basis and applicable riders. OCU’s March 2026 notice announces rising commercial charges from October 2026 with meter-dependent exceptions and separate surcharge changes. It demonstrates why a current bill and a future rate schedule matter; it does not validate the case’s $0.009 per-gallon assumption.

Enter each accepted scope into the opening budget, then rerun the monthly cash model. Base contingency is already modeled as spent; outside upgrades cannot be assumed covered by cash that no longer exists. Recheck the funding bridge if cost, rent-start date or debt payment timing changes. The inspection is complete only when evidence supports the selected design and someone owns every unresolved cost and timing condition.

Sources and scope

App coming soon

Start with your business.

Prepare a planning brief for your project.

The personalized plan generator is being built. You can prepare the information it will need:

  1. Your business format, location and opening scope.
  2. Supplier quotes, operating assumptions and owner contribution.
  3. Your funding goal and any instructions from your lender.
Open the preparation checklist

No order is placed and no payment is taken here.