What does opening this laundromat cost?
Illustrative case · Leased coin/card laundromat; no dry cleaning or wash-and-fold · Illustrative unincorporated Orange County, Florida, United States; no selected premises
Explore this business · Startup costs
The illustrative opening budget is $650,630, including $558,630 of installed assets and fully spent construction contingency, $60,000 of cash reserve, deposits, stock and preopening expenses. This is a bottom-up planning allowance for a compatible leased unit. No contractor, utility or distributor has quoted this complete project; a retail machine price cannot validate the total.
Price a compatible conversion, not an empty-shell promise
The scope is a 2,000-square-foot existing leased unit in unincorporated Orange County, Florida, with practical on-site routes for 24 hardmount washers and eight gas stack dryers. There is no land, building purchase or acquired customer book. The case assumes utilities can serve the site with the inside-unit work listed below. Major external water/sewer mains, gas-network extension, transformer works, structural remediation and hazardous-material remediation are excluded and can invalidate the case.
The 20-lb, 40-lb, 60-lb and dryer sheets support reference capacities and utility design inputs. They provide no public delivered/installed fleet quotation. Confirm current equipment availability, compatible payment options, warranty commissioning requirements and supplier lead times before making the quote schedule binding.
The opening uses and the boundaries of each amount
| Use | Quantity / basis | Budget | Scope boundary |
|---|---|---|---|
| 20-lb washers | 12 × $6,500 | $222,000 is the full three-size fleet | Machine allowances, not an installed quotation |
| 40-lb washers | 8 × $10,500 | Included in washer fleet | Confirm controls, voltage and anchoring |
| 60-lb washers | 4 × $15,000 | Included in washer fleet | Demand and slab conditions must support size |
| Gas stack dryers | 8 × $11,500 | $92,000 | 16 pockets; reader endpoints separate |
| Payment endpoints + kiosk | 40 × $275 + $6,000 | $17,000 | Reader compatibility/processor terms unquoted |
| Water-heating plant | One quoted-design target | $20,000 | Equipment budget; piping in trade schedule |
| Folding/seating/carts/signage | One itemized set to procure | $8,000 | No independently priced furniture bill |
| Water/heater distribution | Defined trade scope | $27,000 | Backflow/valves/inside piping |
| Drainage/slab reinstatement | Defined trade scope | $25,000 | Inside drains; external main excluded |
| Gas / electrical / exhaust | Three coordinated scopes | $12,000 / $18,000 / $17,000 | External gas/transformer capacity excluded |
| General interior finish | Accessible circulation/restroom allowance | $12,000 | Existing compatible shell assumed |
| Delivery, offload, set and commission | Full fleet vendor scope | $15,000 | Do not duplicate trade connections |
| Equipment tax allowance | 7.0% × $359,000 | $25,130 | Budget proxy; actual invoice/surtax treatment unknown |
| Spent construction contingency | 10.0% × equipment/trades/delivery | $48,500 | Fully spent/capitalized in case, not cash reserve |
| Refundable deposits / initial stock | Held assets | $9,000 / $3,000 | No recovery proceeds assumed |
| Preopening expense / financing fees | Expense at closing | $13,000 / $7,000 | Includes paid setup/training; fee budget not SBA quote |
| Opening unrestricted cash | Monthly trough tested | $60,000 | Available after all modeled opening spending |
| Total opening uses | All lines, one scope | $650,630 | Installed CAPEX $558,630 plus other uses |
The largest non-reserve uses are the washer fleet $222,000, site trades $111,000 and dryers $92,000. Each needs a complete specification and a quote, not a general construction benchmark. The modeled tax is an allowance and does not implement Florida per-item surtax rules. Loan fees are a planning budget; obtain the lender’s actual schedule. These limitations sit beside the amounts because they determine whether funding is enough.
Reserve comes from the monthly trough
The $60,000 reserve is cash remaining after opening expenses and capital purchases. Base minimum cash across opening and 60 months is $38,586; Year 1 net cash change after operating costs, tax, principal and timing is −$11,886. The reserve protects a modeled ramp, not unlimited cost overruns or an arbitrary number of profitable months.
Card receipts have a two-day month-end receivable assumption and utilities are paid one month in arrears. Wages, rent, routine maintenance, marketing and other operating costs are paid in their forecast month. The cash balance temporarily benefits from the utility payable; that bill still has to be paid. If a processor settles at ten rather than two days, Month 12 cash falls by $3,633 with no improvement or deterioration in EBITDA.
Downside installed CAPEX rises to 110.0% of base, opening is delayed two months and committed base funding stays fixed. Its initial target-reserve shortfall and later operating losses produce a 60-month additional funding need of $419,059. The first forecast month is already unfunded. Obtain revised funding or reject the scope; the model does not silently borrow to make the bank balance positive.
Request comparable bids and preserve exclusions
Give each bidder the same quantities, model/control/voltage options, floor plan and service point. Ask the distributor for equipment, readers, freight, offload, anchoring, startup, warranty conditions and payment milestones. Ask each trade to state inside versus outside work, demolition/slab reinstatement, pipe/duct routes, permit/design fees, utility connection/impact charges and landlord work. Assign connections once: the vendor’s setting/commissioning allowance is separate from the plumbing/electrical/gas contracts.
A primary pre-owned supplier listing shows a used Dexter T350 Express 20-lb washer at $3,250. It is a different extraction configuration, condition and delivery scope from the assumed new 20-lb budget of $6,500. Replacing twelve new-machine assumptions with a used asking price would need condition inspections, remaining life, matched mix, warranty and installation evidence, then a complete rerun. It is a procurement comparison, not a cost saving already achieved.
A scope register should show quote requested, received, technically checked, accepted and paid as separate dates. A contractor estimate cannot substitute for a utility’s external-capacity confirmation. The official permit process identifies an application route; the actual approved design, fees and inspection sequence remain address-specific.
Items that require a revised model
Obtain actual service tariffs, demand/fixed charges, water/sewer billing rules and connection fees. Orange County Utilities’ notice identifies rising commercial charges, with meter-dependent exceptions; it does not validate the case’s blended tariff. Add outside upgrades, required fire/accessibility work, longer preopening rent, disputed landlord contributions, sales-tax differences or financing-fee changes to their own lines before rerunning the model.
The reserve does not include personal living costs or owner tax payments. No salvage, deposit refund, terminal property value, dry cleaning, delivery vehicle, acquisition goodwill or revenue from services not in the case is assumed. Routine repairs are in operating expenses; capital improvements in months 25 and 49 are separate cash outlays. A future full-fleet replacement study needs a longer horizon and actual remaining-life evidence.
Validate the case inputs
Download the input and evidence register (CSV). This case export separates observed context from assumptions and leaves quotation fields blank for your project. It is an educational register, separate from the planned personalized model.
Sources and scope
- Business Plan Library: planning-case methodology · Checked 2026-10-04 · Illustrative input methodology. Actual laundromat inputs live in the private checked dossier; methodology does not substantiate a local price, quote or demand forecast.
- Dexter T-300 C-Series vended washer specification, Part 0995-113-001 · Checked 2026-10-04 · 20-lb reference configuration; approximately 15.8 US gallons/cycle, 30–120 psi, 3/4-inch inlets. Technical specification is not a current sale/installation quote.
- Dexter T-600 C-Series vended washer specification, Part 0995-113-003 · Checked 2026-10-04 · 40-lb reference configuration; approximately 35.1 US gallons/cycle; selected -12 configuration shows 208–240V/60Hz, 15A branch protection and 6.2A running current. Installer determines actual circuits.
- Dexter T-900 C-Series vended washer specification, Part 0995-113-004 · Checked 2026-10-04 · 60-lb reference configuration; approximately 52.6 US gallons/cycle. Installation, slab/anchoring, drainage and electrical conditions need design.
- Dexter T-30x2 C-Series vended gas stack specification, Part 0995-113-011 · Checked 2026-10-04 · 60Hz, two 30-lb pockets; 90,000 Btu/h input and 600 cfm per pocket, 0.5 hp motor, natural-gas inlet 5–10 inches water column. Specifications are configuration-dependent.
- Systems Engineering Group: pre-owned equipment shop · Checked 2026-10-04 · US seller listing observed 4 October 2026: used Dexter T350 Express 20-lb 200G washer listed at USD 3,250, House Springs MO pickup/shipping availability. Condition/delivery/installation/tax unquoted.
- So Fresh N So Clean: published self-service prices · Checked 2026-10-04 · Rochester-region New York operator, checked 4 October 2026: listed 20/40/60-lb wash prices USD 4.75/7.50/9.50; 30-lb dryer 19 minutes per USD 1. Local demand and Florida prices not established.
- Florida Commerce: Florida minimum wage · Checked 2026-10-04 · Current non-tipped floor USD 15/hour effective 30 September 2026 through 31 December 2027. Case wage USD 18/hour is an assumption, not a local occupation median.
- Orange County Tax Collector: obtaining a new business tax receipt · Checked 2026-10-04 · Illustrative jurisdiction is unincorporated Orange County, Florida. Proposed new businesses require zoning approval before county BTR; municipal parcels follow their own sequence.
- Orange County: plumbing permit process · Checked 2026-10-04 · Commercial plumbing alteration/repair application route, project and contractor details. Process information does not confirm permit scope or fee for a laundromat address.
- Orange County Utilities: commercial rate increase notice, March 2026 · Checked 2026-10-04 · Notice announces changes from 1 October 2026; water/wastewater volume generally rises 11% annually for five years, with small-meter exception and separate fixed/surcharge changes. No assigned account or bill quotation.
- SBA: 7(a) loans · Checked 2026-10-04 · Official program overview inspected 4 October 2026; working capital, machinery purchase/installation and mixed project uses may fit. Lender determines eligibility, documents and repayment.